Construction Update 02-25-2016

The test pile for the north abutment has been driven and production pile installation is expected to follow in the coming weeks. The north abutment excavation is ongoing along with the associated bracing. The contractor continues forming and pouring the concrete for the west retaining wall on the west side of Washington Street. The contractor continues to excavate for the west retaining wall with production pile driving following directly behind. Other ongoing construction activities include the installation of the mechanical elements of the pump station.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 02-19-2016

The contractor has completed the excavation of the material within the sheet pile for the south abutment. The test pile for the south abutment has also been completed with production pile installation anticipated to begin next week. The north abutment sheeting installation is complete with excavation ongoing and a test pile scheduled for next week. The contractor continues forming and pouring the concrete for the west retaining wall on the west side of Washington Street this week. Other ongoing construction activities include the installation of the mechanical elements of the pump station.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 02-09-2016

The contractor continues to excavate the material within the sheet pile for the south abutment, reinforcing the sheeting as the excavation progresses. The north abutment sheeting installation is complete. Once the abutments have been fully excavated the H-Piles will then be driven. The contractor has begun forming and pouring the concrete for the west end of the retaining wall on the west side of Washington Street. Other ongoing construction activities include the installation of the mechanical elements of the pump station.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 02-02-2016

The contractor has begun excavating the material within the sheet pile for the south abutment, reinforcing the sheeting as the excavation progresses. The north abutment sheeting installation is ongoing. Once the abutments have been fully excavated the H-Piles will then be driven. The contractor has begun forming and pouring the concrete for the west end of the retaining wall on the west side of Washington Street this week. Other ongoing construction activities include the installation of the mechanical elements of the pump station.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 01-27-2016

The contractor started the sheet pile installation for the north abutment. Once the sheeting has been installed the material within the sheeting can be excavated and H-Piles can be driven. Additional crews will begin forming and pouring the concrete for the west end of the retaining wall on the west side of Washington Street this week. Other ongoing construction activities include the installation of the mechanical elements of the pump station.

Work Zone Cameras can be viewed under the Photos Tab on the website.