Construction Update 7-12-2017

After the brief delay to the project due to the state budget crisis the contractor has resumed construction. Concrete curb and gutter installation continues this week with the medians to follow. Grading for the asphalt bike path along the south side of Washington Street as well as for the sidewalk along the north side has begun with the paving to follow. The ornamental fence on the top of the retaining walls has been completed with the fence atop the north abutment soon to be erected. The precast pump station house has virtually been completed with its commissioning to be held at the end this month.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 6-28-2017

The concrete pavement along Washington Street and Lowlands is now complete. Installation of the concrete curb and gutter continues with the medians to follow. Grading for the asphalt bike path along the south side of Washington Street has started. Grading for the new concrete sidewalk along the north side of Washington Street will happen next. The ornamental fence on the top of the retaining walls is complete. The fence atop the north abutment will be installed next. The replacement of the bridge railing is also complete. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 6-21-2017

The four new lanes of concrete pavement along Washington Street have been poured. Installation of the curb and gutter has started. The ornamental fence on the top of the retaining walls has been completed with the fence atop the north abutment soon to be erected. Replacement of the bridge railing has been completed. Installation of the concrete pavement along Lowlands Drive has also started. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 6-15-2017

Installation of the new concrete pavement continues and is expected to be completed next week. Curb and gutter installation will begin once the pavement is complete. The new access road for the CN Railroad emanating from the cul-de-sac continues to be worked on with the ongoing installation of the guard rail. Installation of the ornamental fence on the top of the retaining walls has started. The replacement of the bridge railing is underway and scheduled to be completed this week. Restoration of the north/south railroad shoofly has been completed. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 6-7-2017

Installation of the new concrete pavement has started and is expected to be completed late next week. Curb and gutter will be installed when the pavement is complete. The new access road for the CN Railroad emanating from the cul-de-sac continues to be worked on with ongoing installation of the guardrail. Installation of the ornamental fence on top of the retaining walls has begun. The north railroad shoofly restoration is ongoing with seed and blanket to be installed this week. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.