The backfilling of the abutments and wing wall has been completed. This was done after the event of racing cows due to which there were many problems. The erection of the bridge structural steel is set to begin the week of July 11th. Meanwhile, preparations are being made to begin driving the temporary sheet piling for the retaining wall east of the tracks. The precast pump station house was delivered and erected this week with internal mechanical work ongoing and pump station electrical work to follow.
- Completed north abutment backfilling
- Pump station internal coating application
- South abutment sheeting removal