Construction Update 9-6-2017

Restoration continues with seeding and blankets being installed throughout the project limits. The final portion of Lowlands Drive has begun to be installed with final paving scheduled for next week. The balance of the median west of Haryan Way is also scheduled to be completed next week. The tie in pieces of curb and gutter has been poured with their associated sidewalk schedule to be constructed next week. The asphalt resurfacing of Washington Street through the intersection of Lake Street is also scheduled for next week. The driveway for the pump station has been completed.

The work being completed along the northeast corner of Lake and Washington Streets is under a separate contract not affiliated with this grade separation project.

The work being completed along the northeast corner of Lake and Washington Streets is under a separate contract not affiliated with this grade separation project.

Work Zone Cameras can be viewed under the Photos Tab on the website.