Construction Update 7-19-2017

The contractor has resumed construction after a brief delay due to the major rain event. The concrete curb and gutter will continue to be installed this week with median installation to follow. The grading for the asphalt bike paths along the north and south side of Washington Street continues with paving to follow. The ornamental fence on the top of the retaining walls has been completed with the fence atop the north abutment soon to be erected. The staining of the retaining walls and abutments is scheduled to begin next week. The precast pump station house has virtually been completed with its commissioning to be held at the end this week.

Work Zone Cameras can be viewed under the Photos Tab on the website.