Construction Update 7-12-2017

After the brief delay to the project due to the state budget crisis the contractor has resumed construction. Concrete curb and gutter installation continues this week with the medians to follow. Grading for the asphalt bike path along the south side of Washington Street as well as for the sidewalk along the north side has begun with the paving to follow. The ornamental fence on the top of the retaining walls has been completed with the fence atop the north abutment soon to be erected. The precast pump station house has virtually been completed with its commissioning to be held at the end this month.

Work Zone Cameras can be viewed under the Photos Tab on the website.