Construction Update 6-15-2017

Installation of the new concrete pavement continues and is expected to be completed next week. Curb and gutter installation will begin once the pavement is complete. The new access road for the CN Railroad emanating from the cul-de-sac continues to be worked on with the ongoing installation of the guard rail. Installation of the ornamental fence on the top of the retaining walls has started. The replacement of the bridge railing is underway and scheduled to be completed this week. Restoration of the north/south railroad shoofly has been completed. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.