Construction Update 3-6-2017

The stage 2 north abutment has been completed and backfilled. The stage 2 south abutment and the remaining retaining wall have been completed with their backfilling to occur this week. Restoration of the north shoofly restoration has begun. The new temporary access road for the CN railroad emanating from the cul-de-sac has been completed. This road will be used by the CN railroad to access the tracks south of Washington Street. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.