Construction Update 2-14-2017

The stage 2 north abutment, inclusive of the east wing wall, has been constructed with its backfilling to occur in the next few weeks. The south abutment stage 2 footing has been poured with the abutment stem to follow along with the balance of the east retaining wall. Removal of the temporary Metra platform has begun, with the north railroad shoofly restoration to follow. The storm sewer continues to be installed along the west end of the project. The new temporary access road for the CN railroad coming from the cul-de-sac has been completed. This road will be used by the CN railroad to access the tracks south of Washington Street. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.