Construction Update 2-1-2017

The contractor has finished pouring the north abutment. The east wing wall was poured today. Construction has begun on the balance of the east retaining wall/stage 2 of the south abutment. The support of excavation has been installed with the installation of the remaining H piles to follow next week. Storm sewer installation behind the east retaining wall has begun. The new temporary access road for the CN railroad coming from the cul-de-sac has been completed. This road will be used by the CN Railroad to access the tracks south of Washington Street. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.