Construction Update 12-20-2016

The H-piles have begun to be installed for the north abutment with its forming and pouring to follow. The new CN access road emanating from the north end of the cul-de-sac will begin to be installed once the east retaining wall has been adequately backfilled. The embankment that supported the railroad shoofly track south of Washington Street has started to be removed. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

There will be no scheduled work on site between Thursday, December 22, 2016 and Monday, January 2, 2017.  Work will resume on Tuesday, January 3, 2017.

Work Zone Cameras can be viewed under the Photos Tab on the website.