Construction Update 11-22-2016

Installation of the retaining wall east of the railroad bridge continues. Once this is complete, the new CN access road emanating from the north end of the cul-de-sac will begin to be installed. The temporary soil retention system continues to be installed near the north side of the bridge, and braced excavation is occurring in preparation for extending the north abutment. The west retaining wall is being backfilled with topsoil with reparations to fences occurring. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.