Construction Update 11-15-2016

Installation of the retaining wall east of the railroad bridge continues. The temporary soil retention system continues to be installed near the north side of the bridge, and braced excavation is occurring in preparation for the extension of the north abutment. The west retaining wall is being backfilled with topsoil. Detailing the precast pump station house continues. The electrical and mechanical components of the pump station continue to be installed.