Construction Update 09-22-16

Last weekend the west railroad crossing was raised to meet the new railroad track profile. The balance of the existing track is currently being raised with new track being installed over the bridge. The switching of the trains back to their original alignment is scheduled to take place on Saturday, October 1st. Once the trains are switched over to their original alignment, the balance of the east retaining wall and abutments will be constructed. Meanwhile the backfilling of the portion of the east retaining wall that has been built has started. The precast pump station house continues to be detailed. The electrical and mechanical components of the pump station continue to be installed.

Work Zone Cameras can be viewed under the Photos Tab on the website.