Construction Update 08-18-2016

The erection of the bridge structural steel has begun. The main girders were set on Tuesday with the balance of the steel being set over the next few weeks. The installation of the piles for the east retaining wall will be on hold until the structural steel has been erected and the train traffic switched back to its original alignment. Meanwhile the footings for the east retaining wall continue to be formed and poured with the retaining wall panels to follow. The precast pump station house continues to be detailed. The electrical and mechanical components of the pump station continue to be installed. Maintenance on the wetland plants installed in the basin at the northwest quadrant of Washington Street and Lake Street is ongoing.