Construction Update 06-30-2016

The backfilling of the abutments and wing wall has been completed. The erection of the bridge structural steel is set to begin the week of July 11th. Meanwhile, preparations are being made to begin driving the temporary sheet piling for the retaining wall east of the tracks. The precast pump station house was delivered and erected this week with internal mechanical work ongoing and pump station electrical work to follow.

Work Zone Cameras can be viewed under the Photos Tab on the website.