Construction Update 06-16-2016

Backfilling of the abutments will start this week. Once this is complete most of the sheeting around the abutments can be removed and the structural steel set. This is anticipated to begin within the next two weeks. The storm sewer behind the west retaining wall has been completed. The contractor has begun backfilling in front of the west retaining wall. Meanwhile, preparations are being made to begin driving the temporary sheet piling for the retaining wall east of the tracks. The precast pump station house is scheduled to be delivered Friday with its assembly to follow.

Work Zone Cameras can be viewed under the Photos Tab on the website.