Construction Update 06-08-2016

With the completion of the Stage 1 north and south abutments, the next step will be to backfill each abutment and remove the sheeting. Once this is completed the structural steel will be erected. This is anticipated to begin within the next two to three weeks. Installation of the storm sewer behind the west retaining wall has begun. Meanwhile, preparations are being made to begin driving the temporary sheet piling for the retaining wall east of the tracks. The precast pump station house is scheduled to be delivered mid-June.

Work Zone Cameras can be viewed under the Photos Tab on the website.