Construction Update 06-01-2016

The Stage 1 north abutment, south abutment, and west wing wall have been completed. The last panel of the west retaining wall has been completed. The back of the south and north abutment as well as the west retaining wall continue to be backfilled with its drainage system being installed concurrently. As the retaining wall is backfilled the temporary sheet pile is being removed. The structural steel is tentatively scheduled to be set the week of June 13th. The precast pump station house is scheduled to be delivered mid-June.

Work Zone Cameras can be viewed under the Photos Tab on the website.