Construction Update 05-18-2016

Stage one of the north abutment, south abutment and west wing wall have been completed. The last of the west retaining wall piles are completed with the wall footing to be poured this week and the wall pour to follow. The back of the south abutment as well as the west retaining wall continue to be backfilled with its drainage system being installed concurrently The structural steel is tentatively scheduled to be set at the beginning of next month. The precast pump station house is scheduled to be delivered at the end of this month. The reshaping of the west edge of the retention basin along Haryan Way has been completed with the permanent seeding for that basin as well as the basin along Lake Street being completed this week.