Construction Update 05-10-2016

The north abutment west wingwall is currently being formed with its concrete pour scheduled for tomorrow. Backfilling of the back of the south abutment as well as the west retaining wall has begun along with their drainage systems being installed. The last 6 retaining wall piles are scheduled to be driven tomorrow with the pouring of the footing and wall panel to follow. The structural steel is tentatively scheduled to be set at the end of the month. The precast pump station house is also scheduled to be delivered at the end of this month. The reshaping of the west edge of the retention basin along Haryan Way has been completed with its seeding scheduled for Monday.

Work Zone Cameras can be viewed under the Photos Tab on the website.