Construction Update 05-03-2016

The north and south abutment concrete stems have been completed. The next step is to set the structural steel bridge and complete the west wing wall. This is scheduled for the 3rd or 4th week of May. Only one panel of the west retaining wall remains to be completed. When the remaining piles are driven, the panel can be formed and then poured. Other ongoing construction activities include mechanical elements of the pump station and storm water structure installation near Haryan Way. Delivery of the precast pump station house is scheduled for the end of this month.