Construction Update 04-28-2016

The south abutment concrete stem has been completed. The north abutment stem formwork and rebar are currently being installed. The concrete pour is scheduled for early next week. Construction on the west retaining is ongoing with sixteen of the twenty wall panels completed. Other ongoing construction activities include mechanical elements of the pump station and storm water structure installation near Haryan Way.

Work Zone Cameras can be viewed under the Photos Tab on the website.