Construction Update 04-21-2016

The rebar and formwork for the south abutment stem has been completed. The north abutment pile cap has been completed with the abutment stem rebar and formwork to start today. Construction on the west retaining is ongoing with several wall panels completed including two panels poured yesterday. Other ongoing construction activities include mechanical elements of the pump station and storm water structure installation near Haryan Way.

 