Installation of the north abutment piles continues. The pile cap for the south abutment has been formed and the rebar has been installed. The south abutment is scheduled to be poured this week. The retaining wall immediately west of the railroad tracks continues to be formed and poured in 30 foot long panel segments.  Installation of the pump station mechanical elements is ongoing.      

 