Construction Update 03-09-2016

Pile length determination for the abutments is ongoing. Once this is complete and the pile procedure established, installation will begin. Excavation of the north abutment is ongoing along with the associated bracing. The contractor continues forming and pouring the concrete for the west retaining wall on the west side of Washington Street. The ‘mock-up’ for the architectural reveal for the retaining wall was poured yesterday. Other ongoing construction activities include the installation of the mechanical elements of the pump station.