Construction Update 02-02-2016

The contractor has begun excavating the material within the sheet pile for the south abutment, reinforcing the sheeting as the excavation progresses. The north abutment sheeting installation is ongoing. Once the abutments have been fully excavated the H-Piles will then be driven. The contractor has begun forming and pouring the concrete for the west end of the retaining wall on the west side of Washington Street this week. Other ongoing construction activities include the installation of the mechanical elements of the pump station.