Construction Update 01-19-2016

The contractor continues installing the temporary sheeting for the south abutment. After the south abutment sheeting is complete the sheeting for the north abutment will commence. Once the sheeting has been installed the material within the sheeting can be excavated and H-Piles can be driven. Other ongoing construction activities include the installation of the mechanical elements of the pump station.

Work Zone Cameras can be viewed under the Photos Tab on the website.