Construction Update 01-07-2016

The installation of the H-pile for the west retaining wall has been put on hold. The contractor will now focus their efforts on the installation of the bridge abutments. This work will include the installation of the temporary sheeting with excavation and pile driving to follow. The installation of the mechanical elements of the pump station has begun.

West retaining wall

West retaining wall

Pump station mechanical work

Pump station mechanical work

Work Zone Cameras can be viewed under the Photos Tab on the website.