Construction Update 4-26-2017

The north shoofly restoration is ongoing with its topsoil, seed and blanket to be installed this week. The final excavation for Washington Street is underway. Restoration behind the west retaining wall will start this week with landscaping to follow. The new access road for the CN Railroad emanating from the cul-de-sac has resumed. The landscaping along the south shoofly is scheduled for next week. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 4-19-2017

The north shoofly restoration is ongoing with its topsoil, seed, and blanket to be installed next week. The next major task for the project will be to continue excavating Washington Street which is tentatively scheduled to begin next week weather permitting. The new access road for the CN Railroad emanating from the cul-de-sac has resumed. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 4-11-2017

The north shoofly restoration is ongoing. The next major task for the project will be to continue excavating Washington Street which is tentatively scheduled to begin next week weather permitting. The new access road for the CN Railroad emanating from the cul-de-sac has been completed in a temporary condition with the permanent work scheduled to resume next week. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 4-4-2017

The north shoofly restoration has begun but may be intermittent due to the rain. The next major task for the project will be to continue excavating Washington Street. This task, however, is on hold until better consistent weather conditions can be forecasted. It is anticipated this work will resume the 2nd or 3rd week in April. The new access road for the CN Railroad emanating from the cul-de-sac has been completed in a temporary condition with its final completion this spring. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 3-22-2017

The north shoofly restoration was briefly postponed awaiting some direction from the CN Railroad. This work is scheduled to resume Thursday or Friday this week. The next major task for the project will be to continue excavating Washington Street. This task, however, is on hold until better consistent weather conditions can be forecasted. It is anticipated this work will resume the 2nd or 3rd week in April. The new access road for the CN Railroad emanating from the cul-de-sac has been completed in a temporary condition with its final completion anticipated this spring. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.