Construction Update 10-23-2017

The project is mostly complete. The remaining seeding and blanket has been completed. The signal work at the intersection of Lake and Washington Streets is ongoing. Punchlist work will continue.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 10-16-2017

The project is mostly complete. The remaining seeding and blanket is to be installed west of Lowlands this week. The signal work at the intersection of Lake and Washington Streets is underway. Punchlist work will be ongoing.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 10-5-2017

The project is mostly complete with miscellaneous pavement marking installation wrapping up. There still remains some seeding and blanket to be installed west of Lowlands Drive as well as some traffic signal work to be completed at the intersection of Lake and Washington Street. The seeding cannot be installed until October 15th. The Traffic signal work is scheduled to resume next week. Punchlist work will be ongoing.

As of last Friday, the speed limit through the project has been restored to 40 mph.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 9-22-2017

The project continues to be restored with the planting of the trees and shrubs. The resurfacing of Washington Street through its intersection with Lake Street has been completed as well as the final paving of Lowlands Drive. The final striping of the project is scheduled to be completed today. The concrete for the medians and sidewalk has been completed with the exception of the crosswalk at Haryan Way. This is scheduled to be completed next week. The traffic signal work at the intersection of Washington and Lake Street is scheduled for next week.

Please be aware, there continues to be a 35 MPH speed limit throughout the work zone. This work zone speed limit is tentatively scheduled to be in effect through the end of this month.

The work being completed along the northeast corner of Lake and Washington Streets is under a separate contract not affiliated with this grade separation project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 9-14-2017

The project continues to be restored with the planting of the trees and shrubs. The resurfacing of Washington Street through its intersection with Lake Street has begun with the completion of the asphalt milling. The final paving of this area is scheduled to be completed early next week with striping to follow. The final paving of Lowlands Drive is scheduled to take place next week. The balance of the concrete for the sidewalk and medians is scheduled to be installed next week.

Please be aware, there continues to be a 35MPH speed limit throughout the work zone. This work zone speed limit is tentatively scheduled to be in effect through the end of this month.

The work being completed along the northeast corner of Lake and Washington Streets is under a separate contract not affiliated with this grade separation project.

Work Zone Cameras can be viewed under the Photos Tab on the website.