Construction Update 9-14-2017

The project continues to be restored with the planting of the trees and shrubs. The resurfacing of Washington Street through its intersection with Lake Street has begun with the completion of the asphalt milling. The final paving of this area is scheduled to be completed early next week with striping to follow. The final paving of Lowlands Drive is scheduled to take place next week. The balance of the concrete for the sidewalk and medians is scheduled to be installed next week.

Please be aware, there continues to be a 35MPH speed limit throughout the work zone. This work zone speed limit is tentatively scheduled to be in effect through the end of this month.

The work being completed along the northeast corner of Lake and Washington Streets is under a separate contract not affiliated with this grade separation project.

The work being completed along the northeast corner of Lake and Washington Streets is under a separate contract not affiliated with this grade separation project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 9-6-2017

Restoration continues with seeding and blankets being installed throughout the project limits. The final portion of Lowlands Drive has begun to be installed with final paving scheduled for next week. The balance of the median west of Haryan Way is also scheduled to be completed next week. The tie in pieces of curb and gutter has been poured with their associated sidewalk schedule to be constructed next week. The asphalt resurfacing of Washington Street through the intersection of Lake Street is also scheduled for next week. The driveway for the pump station has been completed.

The work being completed along the northeast corner of Lake and Washington Streets is under a separate contract not affiliated with this grade separation project.

The work being completed along the northeast corner of Lake and Washington Streets is under a separate contract not affiliated with this grade separation project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 8-25-2017

The roadway runaround has been removed and restoration is in progress. Installation of the final portion of Lowlands Drive has started. Paving is scheduled to begin next week. Construction of the median west of Haryan Way has started with the curb and gutter to be done this week. The balance of the median is scheduled to be completed next week. The tie in pieces of curb and gutter have been poured. The sidewalk is schedule for next week. Topsoil placement throughout the project continues. The driveway for the pump station is scheduled to be constructed next week.

The work being completed along the northeast corner of Lake and Washington Streets is under a separate contract not affiliated with this grade separation project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 8-18-2017

All four lanes of Washington Street are open. Removal of the roadway runaround has started. The final portion of Lowlands Drive is being installed. The median west of Haryan Way has been excavated and is scheduled to be installed next week. Topsoil placement will continue and excavation of the tie in pieces of curb and sidewalk will start soon. The driveway for the pump station is scheduled to be installed next week.

The work being completed along the northeast corner of Lake and Washington Streets is under a separate contract not affiliated with this project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 8-14-2017

All four lanes of Washington Street are open. The sidewalk along the north side and the bike path along the south side of Washington Street are almost complete. Staining of the walls is complete. The roadway runaround will now be removed, topsoil will continue to be placed, and the tie in pieces of curb and sidewalk will begin to be excavated. The final portion of Lowlands Drive will begin to be installed as well as the proposed median west of Haryan Way. Installation of the pedestrian signals at the intersection of Lake and Washington Streets continues.

Work Zone Cameras can be viewed under the Photos Tab on the website.