Construction Update 6-21-2017

The four new lanes of concrete pavement along Washington Street have been poured. Installation of the curb and gutter has started. The ornamental fence on the top of the retaining walls has been completed with the fence atop the north abutment soon to be erected. Replacement of the bridge railing has been completed. Installation of the concrete pavement along Lowlands Drive has also started. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 6-15-2017

Installation of the new concrete pavement continues and is expected to be completed next week. Curb and gutter installation will begin once the pavement is complete. The new access road for the CN Railroad emanating from the cul-de-sac continues to be worked on with the ongoing installation of the guard rail. Installation of the ornamental fence on the top of the retaining walls has started. The replacement of the bridge railing is underway and scheduled to be completed this week. Restoration of the north/south railroad shoofly has been completed. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 6-7-2017

Installation of the new concrete pavement has started and is expected to be completed late next week. Curb and gutter will be installed when the pavement is complete. The new access road for the CN Railroad emanating from the cul-de-sac continues to be worked on with ongoing installation of the guardrail. Installation of the ornamental fence on top of the retaining walls has begun. The north railroad shoofly restoration is ongoing with seed and blanket to be installed this week. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 5-30-2017

Washington Street has been fully excavated and the aggregate base course placed. The contractor has started the final trimming of the base course with the concrete pour to follow. The new access road for the CN Railroad coming from the cul-de-sac continues to be worked on with the installation of the guard rail today. The ornamental fence on the top of the retaining walls is scheduled to be installed within the next two weeks. The north railroad shoofly restoration is ongoing with topsoil seed and blanket to be installed this week. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 5-24-2017

The final excavation for Washington Street continues with placement of the capping stone. Preparations for the new concrete pavement will begin next week. Construction of the new access road for the CN Railroad emanating from the cul-de-sac continues. The ornamental fence on the top of the retaining walls is scheduled to be installed within the next two weeks. The north railroad shoofly restoration is ongoing with topsoil seed and blanket to be installed next week. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.