Construction Update 12-06-2016

Installation of the retaining wall east of the railroad bridge continues. Once this is adequately completed, the new CN access road emanating from the north end of the cul-de-sac will begin to be installed. The embankment that supported the railroad shoofly track south of Washington Street has started to be removed. The temporary soil retention system continues to be installed near the north side of the bridge, and braced excavation is occurring in preparation for extending the north abutment. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 11-29-2016

Installation of the retaining wall east of the railroad bridge continues. Once this is complete, the new CN access road emanating from the north end of the cul-de-sac will begin to be installed. The temporary soil retention system continues to be installed near the north side of the bridge, and braced excavation is occurring in preparation for extending the north abutment. The west retaining wall is being backfilled with topsoil with reparations to fences occurring. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 11-22-2016

Installation of the retaining wall east of the railroad bridge continues. Once this is complete, the new CN access road emanating from the north end of the cul-de-sac will begin to be installed. The temporary soil retention system continues to be installed near the north side of the bridge, and braced excavation is occurring in preparation for extending the north abutment. The west retaining wall is being backfilled with topsoil with reparations to fences occurring. The precast pump station house has virtually been completed with its commissioning to be held at the end of the project.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 11-15-2016

Installation of the retaining wall east of the railroad bridge continues. The temporary soil retention system continues to be installed near the north side of the bridge, and braced excavation is occurring in preparation for the extension of the north abutment. The west retaining wall is being backfilled with topsoil. Detailing the precast pump station house continues. The electrical and mechanical components of the pump station continue to be installed.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 11-08-2016

The retaining wall east of the railroad bridge continues to be worked. Temporary soil retention system continues to be installed near the north side of the bridge, and braced excavation is occurring in preparation for extending the north abutment. The west retaining wall is being backfilled with topsoil. The precast pump station house continues to be detailed. The electrical and mechanical components of the pump station continue to be installed.

Work Zone Cameras can be viewed under the Photos Tab on the website.